Sioux Falls Custom Builder — Cold-Weather Framing Freeze Loss
Mid-January, a Sioux Falls custom builder had an unheated framed structure suffer a domestic water-line freeze when the temporary heat system failed overnight. Water ran for 14 hours. Damage to subfloor, framing, drywall in finished areas, and electrical rough-in: $186,000. The builder's risk required cold-weather-protocol documentation as a coverage trigger.
Pulled the builder's risk policy and the cold-weather protocol requirements. The contractor had been running protocols but hadn't documented them centrally. Coordinated the documentation submission to the carrier and helped the contractor implement a temperature-monitoring system on every winter framing job.
Builder's risk paid net of deductible after documentation. Subrogation against the temporary heat installer recovered $48,000. Going forward, the contractor's cold-weather protocol is documented continuously. SD winter framing without protocol documentation is one freeze event from a coverage decline.